Construction organization of GEIS-1250 steel slitting machine
To ensure the high quality of this GEIS1250 slitting machine project , The installation precision required on drawing designed is very high, so the requirement of construction is relatively higher. And because The project is constructed in the factory building , there is another production line next to it, which forms the situation of simultaneous production and construction, so the construction site is relatively tight. Therefore during the construction process, we should fully consider that the reasonable allocation of equipment layout and construction land occupation.
The first we should ensure the normal operating of another running machine, then set up a temporary storage to store the spare parts according to site condition. About the main equipment of slitting line should be opened when installed to saving more space.
Due to the high precision requirement of installation, The center marker and reference point must be buried and tested before the installation.it is important to guarantee the continuous running of whole production line, and it also very important to the installation of auxiliary equipment.